<< Show table of contents >> Projects > Opened project > Fundings > Budget structures > Setting up a budget structure |
To set up a new budget structure, complete the fields in the individual sections and click on Save. Note that you must release the budget structures to apply the changes.
Budget structure |
The name of the budget structure is shown in WINPACCS Cloud, WINPACCS Accounting and WINPACCS Cashbook wherever budget lines can be selected. |
|
Budget structure number |
The budget structure number is assigned automatically and cannot be changed. |
|
Mandatory entry |
Here you specify whether a budget line of this budget structure must be assigned to each posting during the posting process or whether it is optional to select the budget structure. |
|
Multiple selection possible |
Here you specify whether several budget lines can be selected in a posting in WINPACCS Accounting and WINPACCS Cashbook. The amount can then be distributed as a percentage to the selected budget lines. If all other posting data is identical, this function replaces the splitting function in accounting. The entries are made directly in the budget structure. Here is an example from WINPACCS Accounting: In Project controlling, these entries are automatically displayed as individual reporting positions.
|
|
Monitoring of quantities |
Here you specify whether the budget structure is used to enter quantities as well as amounts. If the setting is activated, you can determine whether quantities can also be entered in it and specify a unit of measure, individually for each budget line. The units of measure available are defined in the organisational settings for Project controlling. Only one budget structure can be used for monitoring of quantities per project. Once a budget structure has been used for monitoring of quantities, no other budget structure can be used for it during the entire project duration. Changes cannot be made at a later date.
|
|
Activate this setting to link budget lines to cost and income accounts of the main chart of accounts. When posting in WINPACCS Accounting and WINPACCS Cashbook only the linked budget lines are then available, depending on the selected account. This setting helps to meet special donor requirements or to reduce combinations of accounts and budget lines that are incorrect content-wise. If this setting is activated, the column Restriction on accounts is displayed on the Budget lines tab. Assign the appropriate accounts to the postable budget lines there. Cost and income accounts are available.
|
||
Change possible in Project controlling |
Here you specify whether budget lines that were assigned in Project accounting can be corrected in Project controlling or can be changed for evaluation and analysis purposes. The postings in Project accounting remain unchanged. |
|
Postings to budget lines that are no longer postable can be reversed or reposted in WINPACCS Accounting |
Activate this setting, so that postings to budget lines that can no longer be posted to, can still be reversed or reposted in WINPACCS Accounting. If this setting is not activated, the budget line must first be marked again as postable in WINPACCS Cloud, in order to reverse or repost such postings in WINPACCS Accounting. This option is used, for example, to prevent reversals and repostings if the budget structure in question is forwarded to Company accounting via an interface and the budget line is blocked there. This setting can only be edited at this point if it has not already been activated in the organisational settings. |
You can assign a funding to the budget structure. This means that only vouchers which are also assigned to this funding can be assigned to the budget structure during posting. If another funding is selected during posting, the budget structure is not available.
Enter the name of the budget structure in the languages relevant to the project. Depending on the set user language, this translation is displayed in all fields and reports.
Here you define how many levels the budget structure has and how the codes of the budget lines are structured. The following functions are thus available:
Add budget level |
Creates a further budget level. Up to four budget levels are possible. |
|
Delete last budget level |
Deletes the last budget level. |
|
Budget level in other languages |
Opens a window in which you can enter the name of the budget level in other languages. |
The name in the Budget level field is only used for differentiation during setting up and editing the budget structure. This name is not displayed during posting and does not appear in any report.
The number of characters determines how long the code for this budget level is. Codes of budget lines includes all the codes of the budget levels that are superior to them. Here you define the length of the codes of the individual levels that make up the budget line codes.
The following is an example of a budget structure:
In order to create budget lines according to the model shown, the following settings are required:
This configuration allows the Experts / consultants budget line to be given code 1.2.2 on the third level. The structure is as follows:
▪Headline: 1. (two characters) Human Resources
▪Cost category: 2. (two characters) Salaries international staff
▪Detailed cost category: 2 (one character) Experts / consultants